It is important to cooperate already in the design phase
The shaft must de planned to fit the Lift's size
Under the construction of the shaft is important to keep the correct size, the vertical and horizontal surfaces, otherwise the lift will not fit.
The lift presses only the floor. The material of the walls is optional
When both the pit and the lift are completed, the transport and installation takes 1-2 days only
During the installation the area of the pit should be kept free. The scissor part of the lift is over 3tons. It needs a hevy crane to lift it. Usually the delivery truck is equipped with such a crane.
When the scissor part is already in the shaft the lift is eletrcic and hydraulic connected and the functions are controlled
Now can be the extensions installed. After this the columns and the roof
After the lift is ready the main control box and the upper and lover control units will de installed
At last the lift will be tried with a car as well. The lift is ready to handover after every shipping damage is corrected.
Now the roof can be paved or grass can be layed